Wapda exploring avenues to raise $2 billion financing

WAPDA discovers technical issues with K-IV Project

Pakistan Water and Power Development Authority (WAPDA) is concerned about the issues regarding K-IV project. Chairman Pakistan Water and Power Development Authority (WAPDA) Lt Gen Muzammil Hussain (Retd) visited the project site to get a detailed briefing about the steps that need to be taken before the project can proceed.
The chairman was accompanied by a technical team comprising of seasoned and reputed engineers having vast experience in project implementation including Advisor (Projects), General Manager (Coordination & Monitoring) Water, General Manager (Central Design Office), General Manager (Hydro Planning) and General Manager (Projects) South.
K-IV Project Director Government of Sindh made a briefing about the current status of the project, highlighting impediments in the way to construction of the scheme. Frontier Works Organization (FWO) Project Manager informed of the construction progress achieved so far on the project. While OCL Consultants Director made a detailed deliberation about the issues hampering the project.
Chairman WAPDA said that the project could not proceed without resolving technical issues relating to design, route and functionality of Greater Karachi Water Supply Scheme K-IV project.