IT Park in Islamabad continues to hit headlines for slow pace

Report by Engineering Post

The Islamabad Information Technology (IT) Park, Pakistan’s digital strategy  flagship project continues to hit headlines and is  being criticized by official quarters concerned for the  slow  pace of its implementation  and falling behind its scheduled completion.

Being funded through a concessional loan from South Korea was originally scheduled for completion in early 2025 but the multi-million dollar project was running behind  suffering from months of delay.

The Technology  Park Development project Islamabad, as per  the Public Sector Development Programme (PSDP) of the Federal Government as a project of the  Ministry of Information Technology & Telecommunication was approved by  the Executive Committee of National Economic Council (ECNEC)  in  December  2018  for implementation at an estimated cost of Rs  23303.048 million .

The official quarters have sternly warned  South Korean contractor SAMHAN Construction  Corporation, of strict  action if the immediate progress is not ensured  for the project completion at the earliest possible as it was already behind the schedule.

The project is located in Chak Shahzad over an area of  14.9  acres of land and is being implemented at a \total cost of US$ 88.8 million  including US$ 12.5 million local contribution.

It is intended to  attract the international  firms  by providing  a one-step solution  for all problems such as legal, tax, and infrastructure challenges  while boosting  nation IT exports. The facility spans over  an area of 720000  square feet  with  adequate space for  startups  and anchor tenants, a data centre , an auditorium and parking  for 1200 vehicles.

According to the information available from the official sources  concerned,  construction work is about 71 percent  physically complete, with the  gray structure   finished  but mechanical, electrical. and  finishing works  were lagging behind schedule while the official  deadline was October 31,2025.The major  works, according to the contractor,  may only be done  by December 2025, with final  commissioning  expected in February 2026.

The contractor has informed the official concerned about the multiple problems faced  citing these as causes for the delay i.e. unprecedented monsoon  flooding  in 2022, import restrictions  owing to Pakistan’s dollar crisis, and bureaucratic  hurdles  in securing  financial instruments. The contractor reportedly also faced  management challenges internally  such as changing  project managers  nine times within  30 months, along with  cash flow pressures  due to the depreciation of the Korean currency.

The IT Park  remains  central  to Pakistan’s vision  of expanding  its technology exports and attracting  foreign investment,.